Hydropower Development: Target vs Achievement (plan wise)

 

Periodic Plans Target (MW) Achievement (MW) Cumulative achievement(MW)
Before 1st Plan 1.1 1.1 1.1
First  20 0 1.1
Second  22 2.4 3.5
Third  60 0.2 3.7
Fourth  40.3 11 14.7
Fifth  59 15 29.7
Sixth  145 75.6 105.3
Seventh  107 10.1 115.4
Eighth  320.3 20.6 136
Ninth  580 260.2 396.2
Tenth  315 41.2 437.4
11th Plan (Three years Plan) (2007/08-2009/10) 105 77 639.7 (472.9 NEA & 166.8 Private)
12th Plan (Three years Plan) (2010/11-2012/13) 184 64 705 (NEA 473 & 232 Private Sector)
13th Plan (Three years Plan) (2010/11-2012/13) 668    

 

Download Infographic

Source: Various Development Plans