Hydropower Projects Under Construction

Project Name Type Installed Capacity (MW) Annual Energy (GWh) Expected Commercial Operation (2015/16)
Kulekhani III STO 14 40.85 2015/16
Chameliya PROR 30 184.21 2015/16
Khani Khola ROR 25 114 2015/16
Upper Sanjen ROR 11 82.4 2016/17
Sanjen ROR 42.9 251.9 2016/17
Upper Trishuli 3 A ROR 60 489.9 2016/17
Upper Tamakoshi PROR 456 2281 2016/17
Madhya (Middle) Bhotekoshi ROR 102 542 2017/18
Rasuwagadi ROR 111 613.88 2017/18
Rahughat PROR 32 186.12 2017/18
Upper Marsyangdi ROR 50 317 2017/18
Mistri ROR 42 225 2017/18
Upper Trishuli 3 B ROR 37 296.34 2019/20
Upper Modi A ROR 42 214.87 2020/21
Tanahu STO 140 484.4 2020/21
Budhi Gandaki STO 600 2674 2022/23
Total   1794.9 8997.87  
Source: Nepal Electricity Authority 2014